Business days in two weeks
| A | B | |
|---|---|---|
| 1 | Start | End |
| 2 | 3/1/2024 | 3/15/2024 |
Formula: D2: =NETWORKDAYS(A2,B2)
Result: 11
March 1 (Fri) to March 15 (Fri) contains 11 weekdays, counting both ends.
Working days in a period.
NETWORKDAYS(start_date, end_date, [holidays])Example: =NETWORKDAYS(A2,B2,Holidays)
Available in: All versions
NETWORKDAYS counts the working days between two dates, excluding Saturdays, Sundays and an optional list of holidays: =NETWORKDAYS(start_date, end_date, [holidays]). Both the start and end dates are counted if they are working days.
| A | B | |
|---|---|---|
| 1 | Start | End |
| 2 | 3/1/2024 | 3/15/2024 |
Formula: D2: =NETWORKDAYS(A2,B2)
Result: 11
March 1 (Fri) to March 15 (Fri) contains 11 weekdays, counting both ends.
| A | B | C | D | |
|---|---|---|---|---|
| 1 | Start | End | Holidays | |
| 2 | 3/1/2024 | 3/15/2024 | 3/13/2024 |
Formula: F2: =NETWORKDAYS(A2,B2,D2)
Result: 10
The holiday on Wednesday, March 13 removes one more day.
| A | B | |
|---|---|---|
| 1 | Start | End |
| 2 | 3/9/2024 | 3/10/2024 |
Formula: D2: =NETWORKDAYS(A2,B2)
Result: 0
Saturday and Sunday are both excluded.
A tiny spreadsheet with example data. Edit the formula or any number and see the result.
Formula in F2: =NETWORKDAYS(A2,B2,C2:C3)
| A | B | C | D | E | F | |
|---|---|---|---|---|---|---|
| 1 | Start | End | Holiday | Time | Result | |
| 2 | 3/15/2026 | 6/20/2026 | 5/1/2026 | 14:45 | 69 | |
| 3 | 1/31/2026 | 2/28/2026 | 5/9/2026 | 09:30 | ||
| 4 | 12/24/2025 | 1/9/2026 |
Enter — commit · F2 — edit · F4 — $ in a reference · Ctrl+C/Ctrl+V — copy and paste · Ctrl+Z — undo
Esc or F6 — leave the sheet for the «Check» button · Shift+Tab in the first cell — back to the page