  1. In D2:D4, calculate the finish date of each stage, skipping weekends and the holidays in G2:G5.

Lesson theory
  • WORKDAY(start, days, [holidays]) is the date when a job lasting N workdays will be finished;
  • NETWORKDAYS(start, end, [holidays]) is how many workdays there are in a period.

Saturdays and Sundays are skipped automatically. Holidays are passed as a range of dates. Here that is column G.